Our Client.

Engaged by our client as the only external consultant on this major commercial claim, we worked indirectly for the Dubai aviation authorities.

Their Mission.

To review, interrogate and defend a multi-million pound commercial claim from the construction contractor.

Our Role.

Over a seven-month period from March to September 2016, we provided intensive and dedicated quantity surveying and cost management services in support of the preparation and submission of an Expert Witness report by our client.

The Result.

A detailed and extensive Expert Witness report was submitted by our client in November 2016. Due to the commercially sensitive nature of this matter, we are unable to comment further, but along with the other members of the team, we were commended within internal testimonials. Unfortunately, however, we are unable to refer to, or publish, the details of that correspondence.